Construction Update – June 2018

Construction Update – June 2018

Despite some wet weather during the past weeks, the construction of the Coleambally Solar Farm is progressing well. Key construction highlights include:

  • Installation of 100% of piles;
  • Installation of 60%+ of trackers;
  • Installation of 30%+ of all solar panels;
  • Start of all electrical installations;
  • Substation primary equipment installed;